Works on implementing Belekech program go with advance

6 August 2011, Saturday
Funds for holding major repair of multi-apartment houses will be annually provided in the budget of Tatarstan. This has been stated today at a meeting in the RT Government House by RT President R.N. Minnikhanov. By his words, a major repair program should be continued. In this connection head of the republic criticized leadership of some municipal regions where funds collecting for major repairs is arranged poorly or dates of holding repair is not fulfilled at all.

In general, out of 999 multi-apartment houses bound for repairing in 2011 the repair is over in 475 houses ( at 37 municipalities). Out of them in 154 apartment the major repair has been finished for last two weeks, RT Minister of construction, architecture and utilities Irek Faizullin reported at the session.

Out of all house 8031 metering devices planned for installing in 2011, 4444 mounted (55% of the plan),out of them 2039 – central heating, 2384 – water supply, 21 – electric lines.

Irek Faizullin reported also on implementing the Belekech program - provision with places to children’s preschool institutions. So, it has been assumed to make works by August 1 in amount of 1,5 bln. rourbles. Actually, 1,7 bln. rub have been assimilated. (advance in program implementation - 13%).

Out of the objects within the program were returned to the system of preschool education, the repair works are over in Buinsk (3 objects), Kukmor (3 objects),Kazan and others. The works at 11 objects finished more 70%.

Out of 92 objects where the additional places for children to be arranged, 80 have been commissioned. At the remained 12 objects the works approaching the end. Delivery and assembly of equipment is underway.

Head of Tatarstan Rustam Minnikhanov stated that the main goal at these objects to keep in mind is quality of constriction and repair works.