On 6 September, speaking at a regional meeting held by Tatarstan Prime Minister Aleksey Pesoshin in the Government House of the republic, the Director of the Fund “Institute of the Tatarstan Cities Development” Nailya Zinatullina reported that the regional Our Yard Programme 2025 has been completed by 95%, with road work finished by 98 per cent and its completion panned by 30 September and lighting installation completed in 653 yards which is 99 per cent of the planned.
Sports and children’s playground equipment has been installed in 522 yards in 11 regions of the republic and the work is planned to be completed in remaining 115 yards by 20 September.
She also informed about commissioning work carried out in the last two weeks and the typical drawbacks which hamper the work acceptance such as construction waste on the soil, traces of construction machinery of the asphalt and the like.
In conclusion she informed about work done for the implementation of the programme in 2026.